South Dakota regulators refuse to pause on Summit Carbon Solutions’ pipeline permit decision

South Dakota regulators have refused to pause proceedings on Summit Carbon Solutions’ pipeline permits.

They are forcing the company to present its plan for moving forward after a new state law barred its use of eminent domain.
Summit has been seeking this permit for its $9 billion pipeline since 2022. The project would carry carbon dioxide from ethanol plants across five states to underground storage sites in North Dakota.

The company currently has permits in place in North Dakota, Minnesota, and Iowa.

Summit’s attorney argues the company needs more time to consider its options.

Related Stories
While the Farm Bill is top of mind right now, it is far from the only issue getting attention in Washington.
Lewie Pugh, with the Owner-Operator Independent Drivers Association, discusses EPA DEF system changes and what they mean for the supply chain and fuel costs.
JBS says the plant is now operating at full capacity as plant workers return to work.
Rising costs and prices are shifting acreage toward soybeans. Most fertilizer prices are up double digits from this time last year, with Urea seeing the largest gains.
Industry leaders argue the decision could disrupt confidence in conservation practices and increase regulatory uncertainty for producers across the region.
A Nebraska rancher says his land may not support cattle this year after 2,000 acres were burned in recent devastating wildfires across the state.